Permitting Action Modification History

Complete
Consent to easement executed one week earlier than original target date of 12/27/24.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 05-31-2024 05-31-2024 --- Yes
Completed application received (Applicant Action) 11-27-2024 06-19-2024 --- Yes
Issuance of decision for permit/approval (Agency Action 12-27-2024 12-20-2024 --- Yes
In Progress
Application was submitted last summer and determined complete ahead of schedule , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 05-31-2024 05-31-2024 --- Yes
Completed application received (Applicant Action) 11-27-2024 06-19-2024 --- Yes
Issuance of decision for permit/approval (Agency Action 12-27-2024 12-27-2024 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 05-31-2024 05-31-2024 --- Yes
Completed application received (Applicant Action) 11-27-2024 11-27-2024 --- No
Issuance of decision for permit/approval (Agency Action 12-27-2024 12-27-2024 --- No