Permitting Action Modification History

Complete
Section 408 permit was issued more than two months ahead of schedule.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 05-31-2024 05-31-2024 --- Yes
Completeness Determination (Agency Action) 06-13-2024 06-13-2024 --- Yes
Complete application submitted (Applicant Action) 06-21-2024 06-21-2024 --- Yes
Issuance of Decision (Agency Action) 11-26-2024 09-12-2024 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 05-31-2024 05-31-2024 --- Yes
Completeness Determination (Agency Action) 06-13-2024 06-13-2024 --- Yes
Complete application submitted (Applicant Action) 06-21-2024 06-21-2024 --- Yes
Issuance of Decision (Agency Action) 11-26-2024 11-26-2024 --- No