USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Planned
BLM, as part of its standard process for solar projects, requires several baseline studies before beginning NEPA. The Project Sponsor and BLM have worked together to ensure completeness of the required studies and coordinated to manage BLM review and Project Sponsor submittals to maintain progress. Through recent increased coordination, the agency and Project Sponsor agreed that additional time is needed to finalize and approve the required studies.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 02-14-2025 08-11-2025 --- No
Issuance of a Draft EA / Release for Public Review (Agency Action) 08-15-2025 02-25-2026 --- No
Issuance of a Final EA (Agency Action) 10-31-2025 04-24-2026 --- No
EA Process Concluded (Agency Action) 11-30-2025 06-08-2026 --- No
Planned
Adding date for EA Process Concluded.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 02-14-2025 02-14-2025 --- No
Issuance of a Draft EA / Release for Public Review (Agency Action) 08-15-2025 08-15-2025 --- No
Issuance of a Final EA (Agency Action) 10-31-2025 10-31-2025 --- No
EA Process Concluded (Agency Action) 11-30-2025 11-30-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Determination to prepare an Environmental Assessment (EA) (Agency Action) 02-14-2025 02-14-2025 --- No
Issuance of a Draft EA / Release for Public Review (Agency Action) 08-15-2025 08-15-2025 --- No
Issuance of a Final EA (Agency Action) 10-31-2025 10-31-2025 --- No
EA Process Concluded (Agency Action) --- --- --- No