Permitting Action Modification History
Modifications on 11/13/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 02-14-2025 | 09-30-2026 | --- | No |
| Issuance of a Final EA (Agency Action) | 10-31-2025 | 07-29-2027 | --- | No |
| EA Process Concluded (Agency Action) | 11-30-2025 | 08-30-2027 | --- | No |
Modifications on 07/09/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 02-14-2025 | 12-17-2025 | --- | No |
| Issuance of a Draft EA / Release for Public Review (Agency Action) | 08-15-2025 | 07-17-2026 | --- | No |
| Issuance of a Final EA (Agency Action) | 10-31-2025 | 11-16-2026 | --- | No |
| EA Process Concluded (Agency Action) | 11-30-2025 | 12-16-2026 | --- | No |
Modifications on 12/20/2024
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 02-14-2025 | 08-11-2025 | --- | No |
| Issuance of a Draft EA / Release for Public Review (Agency Action) | 08-15-2025 | 02-25-2026 | --- | No |
| Issuance of a Final EA (Agency Action) | 10-31-2025 | 04-24-2026 | --- | No |
| EA Process Concluded (Agency Action) | 11-30-2025 | 06-08-2026 | --- | No |
Modifications on 05/17/2024
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 02-14-2025 | 02-14-2025 | --- | No |
| Issuance of a Draft EA / Release for Public Review (Agency Action) | 08-15-2025 | 08-15-2025 | --- | No |
| Issuance of a Final EA (Agency Action) | 10-31-2025 | 10-31-2025 | --- | No |
| EA Process Concluded (Agency Action) | 11-30-2025 | 11-30-2025 | --- | No |
Modifications on 05/15/2024
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 02-14-2025 | 02-14-2025 | --- | No |
| Issuance of a Draft EA / Release for Public Review (Agency Action) | 08-15-2025 | 08-15-2025 | --- | No |
| Issuance of a Final EA (Agency Action) | 10-31-2025 | 10-31-2025 | --- | No |
| EA Process Concluded (Agency Action) | --- | --- | --- | No |
Modifications on 05/14/2024
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Determination to prepare an Environmental Assessment (EA) (Agency Action) | 02-14-2025 | 02-14-2025 | --- | No |
| Issuance of a Draft EA / Release for Public Review (Agency Action) | 08-15-2025 | 08-15-2025 | --- | No |
| Issuance of a Final EA (Agency Action) | 10-31-2025 | 10-31-2025 | --- | No |
| EA Process Concluded (Agency Action) | --- | --- | --- | No |