Permitting Action Modification History

Planned
Project had been paused. USACE resumed as lead federal agency when pause was lifted. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-03-2025 03-08-2026 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-03-2025 05-18-2026 --- No
Final Verification/Permit Decision Rendered (Agency Action) 02-20-2026 11-19-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-03-2025 11-03-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-03-2025 12-03-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 02-20-2026 02-02-2026 --- No
Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-03-2025 11-03-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-03-2025 12-03-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 02-20-2026 02-02-2026 --- No
Planned
The original target date of 02/20/2026 was entered incorrectly.  The Final Verification/Permit Decision date should have been entered as 02/02/2026 when the Permitting Timetable was initially published.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-03-2025 11-03-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-03-2025 12-03-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 02-20-2026 02-02-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-03-2025 11-03-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-03-2025 12-03-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 02-20-2026 02-20-2026 --- No