USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-02-2025 12-18-2024 --- Yes
Completeness Determination (Agency Action) 10-02-2025 01-16-2025 --- Yes
Complete application submitted (Applicant Action) 11-03-2025 11-03-2025 --- No
Issuance of Decision (Agency Action) 02-02-2026 02-02-2026 --- No
In Progress
Completeness Determination (Agency Action) was completed one day ahead of schedule.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-02-2025 12-18-2024 --- Yes
Completeness Determination (Agency Action) 10-02-2025 01-16-2025 --- Yes
Complete application submitted (Applicant Action) 11-03-2025 11-03-2025 --- No
Issuance of Decision (Agency Action) 02-02-2026 02-02-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-02-2025 12-18-2024 --- Yes
Completeness Determination (Agency Action) 10-02-2025 01-17-2025 --- No
Complete application submitted (Applicant Action) 11-03-2025 11-03-2025 --- No
Issuance of Decision (Agency Action) 02-02-2026 02-02-2026 --- No
Planned
Adjusted to reflect application submittal prior to DEIS NOA.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-02-2025 12-18-2024 --- No
Completeness Determination (Agency Action) 10-02-2025 01-17-2025 --- No
Complete application submitted (Applicant Action) 11-03-2025 11-03-2025 --- No
Issuance of Decision (Agency Action) 02-02-2026 02-02-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 09-02-2025 09-02-2025 --- No
Completeness Determination (Agency Action) 10-02-2025 10-02-2025 --- No
Complete application submitted (Applicant Action) 11-03-2025 11-03-2025 --- No
Issuance of Decision (Agency Action) 02-02-2026 02-02-2026 --- No