Permitting Action Modification History

Complete
Agency was able to complete consultation early., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-12-2023 07-01-2026 --- Yes
Section 106 consultation concluded (Agency Action) 11-03-2025 09-25-2026 --- Yes
In Progress
USACE has not received all the required archeological and historic resources reports from the Project Sponsor in the states of Kansas and Missouri. These reports are required for USACE to make a determination on cultural and historic resources in the permit areas and coordinate the findings and determination with State Historic Preservation Offices (SHPOs) and Tribal Historic Preservation Offices (THPOs). This additional time will allow the project sponsor to complete the reports, submit them to USACE for review, and allow the agencies the necessary time to review and provide comments., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-12-2023 07-01-2026 --- Yes
Section 106 consultation concluded (Agency Action) 11-03-2025 10-01-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-12-2023 07-01-2026 --- Yes
Section 106 consultation concluded (Agency Action) 11-03-2025 08-17-2026 --- No
Planned
Change of lead federal agency and scope of Setion 106 review., basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-12-2023 07-01-2026 --- No
Section 106 consultation concluded (Agency Action) 11-03-2025 08-17-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-12-2023 01-12-2023 --- Yes
Section 106 consultation concluded (Agency Action) 11-03-2025 11-03-2025 --- No
Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-12-2023 01-12-2023 --- Yes
Section 106 consultation concluded (Agency Action) 11-03-2025 11-03-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-12-2023 01-12-2023 --- Yes
Section 106 consultation concluded (Agency Action) 11-03-2025 11-03-2025 --- No