Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 12-16-2022 12-16-2022 --- Yes
Scoping (Agency Action) 02-28-2023 02-28-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 01-17-2025 01-17-2025 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 07-25-2025 07-25-2025 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 11-03-2025 11-03-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 12-16-2022 12-16-2022 --- Yes
Scoping (Agency Action) 02-28-2023 02-28-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 01-17-2025 01-17-2025 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 07-25-2025 07-25-2025 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 11-03-2025 11-03-2025 --- No
Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 12-16-2022 12-16-2022 --- Yes
Scoping (Agency Action) 02-28-2023 02-28-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 01-17-2025 01-17-2025 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 07-25-2025 07-25-2025 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 11-03-2025 11-03-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 12-16-2022 12-16-2022 --- Yes
Scoping (Agency Action) 02-28-2023 02-28-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 01-17-2025 01-17-2025 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 07-25-2025 07-25-2025 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 11-03-2025 11-03-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 12-16-2022 12-16-2022 --- Yes
Scoping (Agency Action) 02-28-2023 02-28-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 01-17-2025 01-17-2025 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 07-25-2025 07-25-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 11-03-2025 11-03-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 12-16-2022 12-16-2022 --- Yes
Scoping (Agency Action) 02-28-2023 02-28-2023 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 01-17-2025 01-17-2025 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 07-25-2025 07-25-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 11-03-2025 11-03-2025 --- No