USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Permitting Action Modification History

Planned
The OCS Air Permit milestones are dependent on BOEM's EIS action milestones. With the shift in the ROD date, EPA will accordingly extend the milestone date for issuance of final decision/permit approval of the OCS Air permit.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 06-23-2024 06-21-2024 --- Yes
OCS Air Permit application submitted (Applicant Action) 12-23-2024 12-20-2024 --- Yes
OCS Air Permit application complete (Applicant Action) 06-23-2025 10-20-2025 --- No
Issuance of final decision/permit approval (Agency Action) 06-23-2026 10-20-2026 --- No
Planned
Application submitted early - 12-20-2024
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 06-23-2024 06-21-2024 --- Yes
OCS Air Permit application submitted (Applicant Action) 12-23-2024 12-20-2024 --- Yes
OCS Air Permit application complete (Applicant Action) 06-23-2025 06-23-2025 --- No
Issuance of final decision/permit approval (Agency Action) 06-23-2026 06-23-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 06-23-2024 06-21-2024 --- Yes
OCS Air Permit application submitted (Applicant Action) 12-23-2024 12-23-2024 --- No
OCS Air Permit application complete (Applicant Action) 06-23-2025 06-23-2025 --- No
Issuance of final decision/permit approval (Agency Action) 06-23-2026 06-23-2026 --- No
Planned
January 19 was incorrectly entered due to a holiday. It should be January 20.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 06-23-2024 06-21-2024 --- No
OCS Air Permit application submitted (Applicant Action) 12-23-2024 12-23-2024 --- No
OCS Air Permit application complete (Applicant Action) 06-23-2025 06-23-2025 --- No
Issuance of final decision/permit approval (Agency Action) 06-23-2026 06-23-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
NOI to apply for an Air Permit submitted (Applicant Action) 06-23-2024 06-23-2024 --- No
OCS Air Permit application submitted (Applicant Action) 12-23-2024 12-23-2024 --- No
OCS Air Permit application complete (Applicant Action) 06-23-2025 06-23-2025 --- No
Issuance of final decision/permit approval (Agency Action) 06-23-2026 06-23-2026 --- No