Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-23-2025 07-24-2026 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-21-2025 10-22-2026 --- No
ESA Consultation Concludes (Agency Action) 01-20-2026 03-22-2027 --- No
Planned
BOEM conducted a comprehensive status of the development of the EIS and found that publication of the Draft EIS on September 19, 2025, is no longer feasible. BOEM estimated that publication of the Draft EIS would be delayed by approximately 10 months (308 day shift) to July 24, 2026. Therefore, subsequently adjusted the remaining milestones for actions accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-23-2025 07-24-2026 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-21-2025 10-22-2026 --- No
ESA Consultation Concludes (Agency Action) 01-20-2026 03-22-2027 --- No
Planned
The ESA milestones "FWS Determines ESA Consultation Package is Complete - Formal" and "ESA Consultation Concludes" are dependent on BOEM’s EIS action milestones. A shift of BOEM’s EIS action milestones by 119 days results in a commensurate shift to these ESA action milestones.  Therefore, an extension is requested based upon the extension of BOEM’s EIS milestones. The , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-23-2025 09-19-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-21-2025 12-18-2025 --- No
ESA Consultation Concludes (Agency Action) 01-20-2026 05-19-2026 --- No
Planned
January 19 was incorrectly entered due to a holiday. It should be January 20. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-23-2025 05-23-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-21-2025 08-21-2025 --- No
ESA Consultation Concludes (Agency Action) 01-20-2026 01-20-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-23-2025 05-23-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 08-21-2025 08-21-2025 --- No
ESA Consultation Concludes (Agency Action) 01-19-2026 01-19-2026 --- No