Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 01-22-2025 01-22-2025 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 07-24-2025 09-24-2026 --- No
ESA Consultation Concludes (Agency Action) 12-22-2025 02-22-2027 --- No
Planned
BOEM conducted a comprehensive status of the development of the EIS and found that publication of the Draft EIS on September 19, 2025, is no longer feasible. BOEM estimated that publication of the Draft EIS would be delayed by approximately 10 months (308 day shift) to July 24, 2026. Therefore, NMFS subsequently adjusted the remaining milestones for NMFS actions accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 01-22-2025 01-22-2025 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 07-24-2025 09-24-2026 --- No
ESA Consultation Concludes (Agency Action) 12-22-2025 02-22-2027 --- No
Planned
BOEM NEPA schedule was extended 119 days, so NMFS milestones adjusted accordingly.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 01-22-2025 01-22-2025 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 07-24-2025 11-20-2025 --- No
ESA Consultation Concludes (Agency Action) 12-22-2025 04-20-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 01-22-2025 01-22-2025 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 07-24-2025 07-24-2025 --- No
ESA Consultation Concludes (Agency Action) 12-22-2025 12-22-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 01-22-2025 01-22-2025 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 07-24-2025 07-24-2025 --- No
ESA Consultation Concludes (Agency Action) 12-22-2025 12-22-2025 --- No