Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-29-2022 07-29-2022 --- Yes
Application deemed complete (Agency Action) 09-29-2022 09-29-2022 --- Yes
Final decision/agency action (Agency Action) 06-23-2026 09-13-2027 --- No
In Progress
BOEM conducted a comprehensive status of the development of the EIS and found that publication of the Draft EIS on September 19, 2025, is no longer feasible. BOEM estimated that publication of the Draft EIS would be delayed by approximately 10 months (308 day shift) to July 24, 2026. Therefore, subsequently adjusted the remaining milestones for actions accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-29-2022 07-29-2022 --- Yes
Application deemed complete (Agency Action) 09-29-2022 09-29-2022 --- Yes
Final decision/agency action (Agency Action) 06-23-2026 09-13-2027 --- No
In Progress
COP final decision/agency action milestone is dependent on the NEPA timeline and affected commensurately by delays. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-29-2022 07-29-2022 --- Yes
Application deemed complete (Agency Action) 09-29-2022 09-29-2022 --- Yes
Final decision/agency action (Agency Action) 06-23-2026 11-09-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-29-2022 07-29-2022 --- Yes
Application deemed complete (Agency Action) 09-29-2022 09-29-2022 --- Yes
Final decision/agency action (Agency Action) 06-23-2026 06-23-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-29-2022 07-29-2022 --- Yes
Final decision/agency action (Agency Action) 06-23-2026 06-23-2026 --- No