Permitting Action Modification History

Complete
Maryland Historic Trust completed their review and provided agency concurrence ahead of schedule.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-15-2025 01-10-2025 --- Yes
Section 106 consultation concluded (Agency Action) 09-15-2025 05-09-2025 --- Yes
In Progress
Consultation initiated on 10 Jan 25 instead of 15 Jan 25. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-15-2025 01-10-2025 --- Yes
Section 106 consultation concluded (Agency Action) 09-15-2025 09-15-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-15-2025 01-15-2025 --- No
Section 106 consultation concluded (Agency Action) 09-15-2025 09-15-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 01-15-2025 01-15-2025 --- No
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) --- --- --- No
Section 106 consultation concluded (Agency Action) 09-15-2025 09-15-2025 --- No