Permitting Action Modification History

Complete
Decision made ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-25-2023 08-25-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-02-2024 12-02-2024 --- Yes
Publication of Public Notice (Agency Action) 01-15-2025 01-10-2025 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-22-2025 12-16-2025 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-25-2023 08-25-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-02-2024 12-02-2024 --- Yes
Publication of Public Notice (Agency Action) 01-15-2025 01-10-2025 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-22-2025 12-22-2025 --- No
In Progress
PN published on 10 Jan 25 instead of 15 Jan 25. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-25-2023 08-25-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-02-2024 12-02-2024 --- Yes
Publication of Public Notice (Agency Action) 01-15-2025 01-10-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-22-2025 12-22-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 08-25-2023 08-25-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-02-2024 12-02-2024 --- Yes
Publication of Public Notice (Agency Action) 01-15-2025 01-15-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-22-2025 12-22-2025 --- No