Permitting Action Modification History

Complete
Ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 12-22-2023 12-18-2023 --- Yes
Scoping (Agency Action) 02-22-2024 02-16-2024 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 01-15-2025 01-10-2025 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 09-22-2025 09-19-2025 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 12-22-2025 12-16-2025 --- Yes
In Progress
Publication was completed early. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 12-22-2023 12-18-2023 --- Yes
Scoping (Agency Action) 02-22-2024 02-16-2024 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 01-15-2025 01-10-2025 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 09-22-2025 09-19-2025 --- Yes
Issuance of Lead Agency Record of Decision (Agency Action) 12-22-2025 12-22-2025 --- No
In Progress
District published DEIS NOA on 10 Jan 25, ahead of 15 Jan 25 original milestone. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 12-22-2023 12-18-2023 --- Yes
Scoping (Agency Action) 02-22-2024 02-16-2024 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 01-15-2025 01-10-2025 --- Yes
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 09-22-2025 09-22-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 12-22-2025 12-22-2025 --- No
In Progress
NOI was issued early so scoping also completed earlier than planned.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 12-22-2023 12-18-2023 --- Yes
Scoping (Agency Action) 02-22-2024 02-16-2024 --- Yes
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 01-15-2025 01-15-2025 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 09-22-2025 09-22-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 12-22-2025 12-22-2025 --- No
In Progress
FR notice published earlier than scheduled.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 12-22-2023 12-18-2023 --- Yes
Scoping (Agency Action) 02-22-2024 02-22-2024 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 01-15-2025 01-15-2025 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 09-22-2025 09-22-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 12-22-2025 12-22-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 12-22-2023 12-22-2023 --- No
Scoping (Agency Action) 02-22-2024 02-22-2024 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 01-15-2025 01-15-2025 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 09-22-2025 09-22-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 12-22-2025 12-22-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 12-22-2023 12-22-2023 --- No
Scoping (Agency Action) 02-22-2024 02-22-2024 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 01-15-2025 01-15-2025 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 09-22-2025 09-22-2025 --- No
Official Notice of Availability of a Supplemental Draft EIS published in the FR (Agency Action) --- --- --- No
Official Notice of Availability of a Supplemental Final EIS published in the FR (Agency Action) --- --- --- No
Issuance of Lead Agency Record of Decision (Agency Action) 12-22-2025 12-22-2025 --- No
Issuance of an Amended Record of Decision (Agency Action) --- --- --- No