Permitting Action Modification History

Complete
EFH Consultation completed early. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 01-15-2025 01-15-2025 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 03-17-2025 03-13-2025 --- Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 05-15-2025 05-08-2025 --- Yes
In Progress
The second EFH milestone was completed four days earlier than planned (3/13/25 instead of 3/17/25). , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 01-15-2025 01-15-2025 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 03-17-2025 03-13-2025 --- Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 05-15-2025 05-15-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 01-15-2025 01-15-2025 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 03-17-2025 03-17-2025 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 05-15-2025 05-15-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 01-15-2025 01-15-2025 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 03-17-2025 03-17-2025 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 05-15-2025 05-15-2025 --- No