Permitting Action Modification History

Complete
consultation concluded early , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 01-15-2025 01-15-2025 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 03-17-2025 03-14-2025 --- Yes
ESA Consultation Concludes (Agency Action) 07-29-2025 05-13-2025 --- Yes
In Progress
The milestone was completed on 3/14 instead of the planned 3/17 target date.   , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 01-15-2025 01-15-2025 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 03-17-2025 03-14-2025 --- Yes
ESA Consultation Concludes (Agency Action) 07-29-2025 07-29-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 01-15-2025 01-15-2025 --- Yes
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 03-17-2025 03-17-2025 --- No
ESA Consultation Concludes (Agency Action) 07-29-2025 07-29-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 01-15-2025 01-15-2025 --- No
NOAA determines ESA Consultation Package is Complete - Formal (Agency Action) 03-17-2025 03-17-2025 --- No
ESA Consultation Concludes (Agency Action) 07-29-2025 07-29-2025 --- No