Permitting Action Modification History
Modifications on 02/06/2024
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| UIC permit application submitted | 03-14-2023 | 03-14-2023 | --- | Yes |
| UIC permit application complete | 05-18-2023 | 05-18-2023 | --- | Yes |
| Issuance of final UIC permit decision | 05-16-2025 | 05-16-2025 | --- | No |
Modifications on 11/09/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| UIC permit application submitted | 03-14-2023 | 03-14-2023 | --- | Yes |
| UIC permit application complete | 05-18-2023 | 05-18-2023 | --- | Yes |
| Issuance of final UIC permit decision | 05-16-2025 | 05-16-2025 | --- | No |
Modifications on 11/09/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| UIC permit application submitted | 03-14-2023 | 03-14-2023 | --- | Yes |
| UIC permit application complete | 05-18-2023 | 05-18-2023 | --- | Yes |
| Issuance of final UIC permit decision | 05-16-2025 | 05-16-2025 | --- | No |
Modifications on 11/09/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| UIC permit application submitted | 03-14-2023 | 03-14-2023 | --- | No |
| UIC permit application complete | 05-18-2023 | 05-18-2023 | --- | No |
| Issuance of final UIC permit decision | 05-16-2025 | 05-16-2025 | --- | No |