Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 11-29-2024 11-29-2024 --- Yes
Completed application received (Applicant Action) 08-25-2025 01-12-2026 --- No
Issuance of final decision/ permit approval (Agency Action) 08-18-2026 01-12-2027 --- No
In Progress
EPA’s OCS air permit and NPDES permit are all dependent on the final completion date for the NEPA action and cross-cutting law actions. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 11-29-2024 11-29-2024 --- Yes
Completed application received (Applicant Action) 08-25-2025 01-12-2026 --- No
Issuance of final decision/ permit approval (Agency Action) 08-18-2026 01-12-2027 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 11-29-2024 11-29-2024 --- Yes
Completed application received (Applicant Action) 08-25-2025 08-25-2025 --- No
Issuance of final decision/ permit approval (Agency Action) 08-18-2026 08-18-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Applicant Action) 11-29-2024 11-29-2024 --- No
Completed application received (Applicant Action) 08-25-2025 08-25-2025 --- No
Issuance of final decision/ permit approval (Agency Action) 08-18-2026 08-18-2026 --- No