Permitting Action Modification History

Complete
The final EFH Milestone was completed two weeks ahead of schedule. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 10-31-2023 10-31-2023 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 12-30-2023 12-20-2023 --- Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 02-28-2024 02-14-2024 --- Yes
In Progress
The milestone for determining the EFH Assessment complete was completed ahead of schedule.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 10-31-2023 10-31-2023 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 12-30-2023 12-20-2023 --- Yes
NOAA Issues any EFH Conservation Recommendations (Agency Action) 02-28-2024 02-28-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 10-31-2023 10-31-2023 --- Yes
NOAA determines EFH Assessment is Complete (Agency Action) 12-30-2023 12-30-2023 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 02-28-2024 02-28-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 10-31-2023 10-31-2023 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 12-30-2023 12-30-2023 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 02-28-2024 02-28-2024 --- No