Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 03-29-2025 03-29-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-28-2025 04-28-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-07-2026 09-07-2026 --- No
Cancelled
USFS was notified via email on 8/8 that the Corps Regulatory issued the approved jurisdictional determination for this project and there are no Section 404 waters within the project area and thus, requested removal of the Corps Regulatory as a cooperating agency.  This also requires removing the action from the project timetable.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 03-29-2025 03-29-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-28-2025 04-28-2025 --- No
Publication of Public Notice (Agency Action) 05-13-2025 05-13-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-07-2026 09-07-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 03-29-2025 03-29-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 04-28-2025 04-28-2025 --- No
Publication of Public Notice (Agency Action) 05-13-2025 05-13-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-07-2026 09-07-2026 --- No