Permitting Action Modification History

Complete
Ahead of schedule , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-19-2023 12-17-2023 --- Yes
Section 106 consultation concluded (Agency Action) 02-10-2026 01-28-2026 --- Yes
In Progress
NOAs publish on the Federal Register on Fridays. Section 106 consultation must be concluded in tandem with draft Record of Decision. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-19-2023 12-17-2023 --- Yes
Section 106 consultation concluded (Agency Action) 02-10-2026 02-06-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-19-2023 12-17-2023 --- Yes
Section 106 consultation concluded (Agency Action) 02-10-2026 02-10-2026 --- No
Planned
Modifying the SHPO consultation initiation date to align with the establishment of a Federal action which would not occur prior to the mine plan of operations being deemed complete (currently planned for 12/17/2023). , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-19-2023 12-17-2023 --- No
Section 106 consultation concluded (Agency Action) 02-10-2026 02-10-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 08-19-2023 08-19-2023 --- Yes
Section 106 consultation concluded (Agency Action) 02-10-2026 02-10-2026 --- No