Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-13-2025 05-13-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-27-2025 07-25-2025 --- Yes
ESA Consultation Concludes (Agency Action) 02-10-2026 02-26-2026 --- Yes
In Progress
Additional time (less than 30 days) needed to address comments submitted by lead federal agency and project sponsor on draft Biological Opinion. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-13-2025 05-13-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-27-2025 07-25-2025 --- Yes
ESA Consultation Concludes (Agency Action) 02-10-2026 02-26-2026 --- No
In Progress
Marking milestone complete earlier than the target date.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-13-2025 05-13-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-27-2025 07-25-2025 --- Yes
ESA Consultation Concludes (Agency Action) 02-10-2026 02-06-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-13-2025 05-13-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-27-2025 07-27-2025 --- No
ESA Consultation Concludes (Agency Action) 02-10-2026 02-06-2026 --- No
Planned
NOAs publish to the Federal Register on Fridays. ESA consultation must be concluded in tandem with the draft Record of Decision. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-13-2025 05-13-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-27-2025 07-27-2025 --- No
ESA Consultation Concludes (Agency Action) 02-10-2026 02-06-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-13-2025 05-13-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-27-2025 07-27-2025 --- No
ESA Consultation Concludes (Agency Action) 02-10-2026 02-10-2026 --- No