Permitting Action Modification History
Modifications on 07/07/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-13-2024 | 05-10-2024 | --- | Yes |
| Scoping (Agency Action) | 02-13-2024 | 05-10-2024 | --- | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 05-13-2025 | 05-09-2025 | --- | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 02-10-2026 | 03-06-2026 | --- | Yes |
| Issuance of Lead Agency Record of Decision (Agency Action) | 07-07-2026 | 07-07-2026 | --- | Yes |
Modifications on 03/06/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-13-2024 | 05-10-2024 | --- | Yes |
| Scoping (Agency Action) | 02-13-2024 | 05-10-2024 | --- | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 05-13-2025 | 05-09-2025 | --- | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 02-10-2026 | 03-06-2026 | --- | Yes |
| Issuance of Lead Agency Record of Decision (Agency Action) | 07-07-2026 | 07-07-2026 | --- | No |
Modifications on 01/05/2026
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-13-2024 | 05-10-2024 | --- | Yes |
| Scoping (Agency Action) | 02-13-2024 | 05-10-2024 | --- | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 05-13-2025 | 05-09-2025 | --- | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 02-10-2026 | 03-06-2026 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 07-07-2026 | 07-07-2026 | --- | No |
Modifications on 05/09/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-13-2024 | 05-10-2024 | --- | Yes |
| Scoping (Agency Action) | 02-13-2024 | 05-10-2024 | --- | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 05-13-2025 | 05-09-2025 | --- | Yes |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 02-10-2026 | 02-06-2026 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 07-07-2026 | 07-07-2026 | --- | No |
Modifications on 04/29/2025
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-13-2024 | 05-10-2024 | --- | Yes |
| Scoping (Agency Action) | 02-13-2024 | 05-10-2024 | --- | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 05-13-2025 | 05-09-2025 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 02-10-2026 | 02-06-2026 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 07-07-2026 | 07-07-2026 | --- | No |
Modifications on 05/10/2024
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-13-2024 | 05-10-2024 | --- | Yes |
| Scoping (Agency Action) | 02-13-2024 | 05-10-2024 | --- | Yes |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 05-13-2025 | 05-13-2025 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 02-10-2026 | 02-10-2026 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 07-07-2026 | 07-07-2026 | --- | No |
Modifications on 07/05/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-13-2024 | 05-13-2024 | --- | No |
| Scoping (Agency Action) | 02-13-2024 | 05-13-2024 | --- | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 05-13-2025 | 05-13-2025 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 02-10-2026 | 02-10-2026 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 07-07-2026 | 07-07-2026 | --- | No |
Modifications on 07/05/2023
Action Level Data
Milestone Level Data
| Milestone | Original Target Date | Current Target Date | Alternative Completion Date | Milestone Complete? |
|---|---|---|---|---|
| Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) | 02-13-2024 | 02-13-2024 | --- | No |
| Scoping (Agency Action) | 02-13-2024 | 02-13-2024 | --- | No |
| Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) | 05-13-2025 | 05-13-2025 | --- | No |
| Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) | 02-10-2026 | 02-10-2026 | --- | No |
| Issuance of Lead Agency Record of Decision (Agency Action) | 07-07-2026 | 07-07-2026 | --- | No |