Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 12-16-2022 12-16-2022 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 12-16-2022 12-16-2022 --- Yes
Section 106 consultation concluded (Agency Action) 07-01-2025 09-29-2025 --- No
In Progress
Section 106 consultation is being conducted through the Section 106 NEPA substitution process and the 106 milestone will shift accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 12-16-2022 12-16-2022 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 12-16-2022 12-16-2022 --- Yes
Section 106 consultation concluded (Agency Action) 07-01-2025 09-29-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 12-16-2022 12-16-2022 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 12-16-2022 12-16-2022 --- Yes
Section 106 consultation concluded (Agency Action) 07-01-2025 07-01-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Consultation initiated with SHPO/THPO (Agency Action) 12-16-2022 12-16-2022 --- Yes
Notification agency will use NEPA substitution approach [36 CFR 800.8(c)] (Agency Action) 12-16-2022 12-16-2022 --- Yes
Section 106 consultation concluded (Agency Action) 07-01-2025 07-01-2025 --- No