Permitting Action Modification History

Cancelled
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 01-31-2024 01-31-2024 --- No
Scoping (Agency Action) 02-28-2024 03-17-2024 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 11-29-2024 11-29-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 07-31-2025 07-31-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 10-31-2025 10-31-2025 --- No
Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 01-31-2024 01-31-2024 --- No
Scoping (Agency Action) 02-28-2024 03-17-2024 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 11-29-2024 11-29-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 07-31-2025 07-31-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 10-31-2025 10-31-2025 --- No
Planned
"Scoping (Agency Action)" This will be a 45-day scoping period, therefore the date of this milestone should be March 17, 2024 rather than February 28, 2024. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 01-31-2024 01-31-2024 --- No
Scoping (Agency Action) 02-28-2024 03-17-2024 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 11-29-2024 11-29-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 07-31-2025 07-31-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 10-31-2025 10-31-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 01-31-2024 01-31-2024 --- No
Scoping (Agency Action) 02-28-2024 02-28-2024 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 11-29-2024 11-29-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 07-31-2025 07-31-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 10-31-2025 10-31-2025 --- No