Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-24-2023 03-24-2023 --- Yes
Application deemed complete (Agency Action) 05-23-2023 05-23-2023 --- Yes
Final decision/agency action (Agency Action) 07-19-2023 07-19-2023 08-24-2023 Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-24-2023 03-24-2023 --- Yes
Application deemed complete (Agency Action) 05-23-2023 05-23-2023 --- Yes
Final decision/agency action (Agency Action) 07-19-2023 07-19-2023 08-25-2023 No
In Progress
The Public Comment Period for Compatibility Determination closed on 6/30/23 and the final compatibility determination will be issued on 7/21/23. Also on 7/21/23 the Request for Appraisal will be sent out and FWS will have the final draft of the Record of Decision.  On 7/31/23, the Special Use Permits on construction will be issued, along with the Right of Way and Notice to Proceed.    , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-24-2023 03-24-2023 --- Yes
Application deemed complete (Agency Action) 05-23-2023 05-23-2023 --- Yes
Final decision/agency action (Agency Action) 07-19-2023 07-19-2023 07-31-2023 No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-24-2023 03-24-2023 --- Yes
Application deemed complete (Agency Action) 05-23-2023 05-23-2023 --- Yes
Final decision/agency action (Agency Action) 07-19-2023 07-19-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 03-24-2023 03-24-2023 --- Yes
Application deemed complete (Agency Action) 05-23-2023 05-23-2023 --- No
Final decision/agency action (Agency Action) 07-19-2023 07-19-2023 --- No