Permitting Action Modification History

Complete
Original target date was 5 July.  District verified NWP on June 1. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 03-21-2023 03-21-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-05-2023 05-05-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 07-05-2023 06-01-2023 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 03-21-2023 03-21-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-05-2023 05-05-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 07-05-2023 07-05-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 03-21-2023 03-21-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-05-2023 05-05-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 07-05-2023 07-05-2023 --- No