Permitting Action Modification History

In Progress
Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents and order, were modified to account for the additional time needed for the project sponsor to file required information, dependent milestone target dates are being modified accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 06-30-2022 06-30-2022 --- Yes
Final decision/agency action (Agency Action) 07-21-2025 12-16-2026 --- No
In Progress
Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents and order, were modified to account for the additional time needed for the project sponsor to complete required studies, dependent milestone target dates are being modified accordingly.     , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 06-30-2022 06-30-2022 --- Yes
Final decision/agency action (Agency Action) 07-21-2025 11-18-2026 --- No
In Progress
Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents, are being modified to account for the additional time needed for the project sponsor to complete required studies, dependent milestone target dates are being modified accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 06-30-2022 06-30-2022 --- Yes
Final decision/agency action (Agency Action) 07-21-2025 02-18-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) --- 06-30-2022 --- Yes
Final decision/agency action (Agency Action) --- 07-21-2025 --- No