Permitting Action Modification History

In Progress
Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents and order, were modified to account for the additional time needed for the project sponsor to complete required studies, dependent milestone target dates are being modified accordingly.    
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-24-2023 08-31-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-08-2023 09-28-2023 --- Yes
Publication of Public Notice (Agency Action) 08-08-2023 10-16-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-23-2024 07-20-2026 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-24-2023 08-31-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-08-2023 09-28-2023 --- Yes
Publication of Public Notice (Agency Action) 08-08-2023 10-16-2023 --- Yes
Final Verification/Permit Decision Rendered (Agency Action) 12-23-2024 10-20-2025 --- No
In Progress
Application materials determined complete on 28 September 2023.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-24-2023 08-31-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-08-2023 09-28-2023 --- Yes
Publication of Public Notice (Agency Action) 08-08-2023 10-16-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-23-2024 10-20-2025 --- No
Planned
The project sponsor has submitted the application day prior to target milestone.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-24-2023 08-31-2023 --- Yes
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-08-2023 10-02-2023 --- No
Publication of Public Notice (Agency Action) 08-08-2023 10-16-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-23-2024 10-20-2025 --- No
Planned
Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents, are being modified to account for the additional time needed for the project sponsor to complete required studies, dependent milestone target dates are being modified accordingly.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-24-2023 09-01-2023 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-08-2023 10-02-2023 --- No
Publication of Public Notice (Agency Action) 08-08-2023 10-16-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-23-2024 10-20-2025 --- No
Planned
Applicant, Corps, and FERC discussed status of project and agreed that due to contractor onboarding timelines, it is appropriate to shift the dates for submittal of a PCN and possible publication of a Public Notice to reflect a more realistic timeline. Applicant continues to work on timely submission of application and ongoing communications remain strong. The final date for rendering a decision are not proposed to change.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-24-2023 09-01-2023 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-08-2023 10-02-2023 --- No
Publication of Public Notice (Agency Action) 08-08-2023 10-16-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) 12-23-2024 12-23-2024 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) --- 07-24-2023 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) --- 08-08-2023 --- No
Publication of Public Notice (Agency Action) --- 08-08-2023 --- No
Final Verification/Permit Decision Rendered (Agency Action) --- 12-23-2024 --- No