Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-15-2024 09-26-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-01-2024 01-09-2026 --- Yes
ESA Consultation Concludes (Agency Action) 09-27-2024 02-26-2026 --- Yes
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-15-2024 09-26-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-01-2024 01-09-2026 --- Yes
ESA Consultation Concludes (Agency Action) 09-27-2024 02-26-2026 --- No
Planned
Commission staff issued the request for formal ESA consultation before the target date.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-15-2024 09-26-2025 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-01-2024 01-09-2026 --- No
ESA Consultation Concludes (Agency Action) 09-27-2024 02-26-2026 --- No
Planned
Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents and order, were modified to account for the additional time needed for the project sponsor to file required information, dependent milestone target dates are being modified accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-15-2024 09-29-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-01-2024 01-09-2026 --- No
ESA Consultation Concludes (Agency Action) 09-27-2024 02-26-2026 --- No
Planned
Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents and order, were modified to account for the additional time needed for the project sponsor to complete required studies, dependent milestone target dates are being modified accordingly.     , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-15-2024 08-29-2025 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-01-2024 12-02-2025 --- No
ESA Consultation Concludes (Agency Action) 09-27-2024 01-26-2026 --- No
Planned
Because the Commission’s milestone target dates, including those for issuance of the draft and final NEPA documents, are being modified to account for the additional time needed for the project sponsor to complete required studies, dependent milestone target dates are being modified accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 05-15-2024 10-25-2024 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-01-2024 01-24-2025 --- No
ESA Consultation Concludes (Agency Action) 09-27-2024 03-24-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) --- 05-15-2024 --- No
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) --- 07-01-2024 --- No
ESA Consultation Concludes (Agency Action) --- 09-27-2024 --- No