Permitting Action Modification History

Paused
project pause , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-01-2024 --- --- No
Completeness Determination (Agency Action) 07-31-2024 --- --- No
Complete application submitted (Applicant Action) 09-29-2024 --- --- No
Issuance of Decision (Agency Action) 10-29-2025 --- --- No
Planned
  The project sponsor’s delayed submission of information needed for a complete Marine Mammal Protection Act (MMPA) Incidental Take Authorization (ITA) application has resulted in delays to the schedule for NMFS’s issuance of the proposed ITA as well as delays to the development of complete Endangered Species Act (ESA) and Essential Fish Habitat (EFH) consultation documents, the Draft Environmental Impact Statement (DEIS), the Final Environmental Impact Statement (FEIS) and all other subsequent dependent milestones. BOEM developed an updated permitting timetable reflecting the 90-day shift to the DEIS, FEIS, and Record of Decision (ROD) milestone dates. The NEPA Action is impacted by the milestone shifts for the ESA Action as a result of the shifts for the MMPA Action; the NEPA timeline is changing accordingly.   Finally, the completion dates for USACE’s Section 408 permit dates are all dependent on the final completion date for the NEPA action. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-01-2024 10-01-2024 --- No
Completeness Determination (Agency Action) 07-31-2024 10-31-2024 --- No
Complete application submitted (Applicant Action) 09-29-2024 12-30-2024 --- No
Issuance of Decision (Agency Action) 10-29-2025 01-27-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 07-01-2024 07-01-2024 --- No
Completeness Determination (Agency Action) 07-31-2024 07-31-2024 --- No
Complete application submitted (Applicant Action) 09-29-2024 09-29-2024 --- No
Issuance of Decision (Agency Action) 10-29-2025 10-29-2025 --- No