Permitting Action Modification History

Planned
  The project sponsor’s delayed submission of information needed for a complete Marine Mammal Protection Act (MMPA) Incidental Take Authorization (ITA) application has resulted in delays to the schedule for NMFS’s issuance of the proposed ITA as well as delays to the development of complete Endangered Species Act (ESA) and Essential Fish Habitat (EFH) consultation documents, the Draft Environmental Impact Statement (DEIS), the Final Environmental Impact Statement (FEIS) and all other subsequent dependent milestones. BOEM developed an updated permitting timetable reflecting the 90-day shift to the DEIS, FEIS, and Record of Decision (ROD) milestone dates. The NEPA Action is impacted by the milestone shifts for the ESA Action as a result of the shifts for the MMPA Action; the NEPA timeline is changing accordingly.   Finally, the completion dates for USACE’s Section 10/404 permit are all dependent on the final completion date for the NEPA action.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-01-2024 10-01-2024 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-01-2024 10-31-2024 --- No
Publication of Public Notice (Agency Action) 08-16-2024 11-15-2024 --- No
Final Verification/Permit Decision Rendered (Agency Action) 10-29-2025 01-27-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-01-2024 07-01-2024 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-01-2024 08-01-2024 --- No
Publication of Public Notice (Agency Action) 08-16-2024 08-16-2024 --- No
Final Verification/Permit Decision Rendered (Agency Action) 10-29-2025 10-29-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 07-01-2024 07-01-2024 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 08-01-2024 08-01-2024 --- No
Publication of Public Notice (Agency Action) 08-16-2024 08-16-2024 --- No
Final Verification/Permit Decision Rendered (Agency Action) 10-29-2025 10-29-2025 --- No