Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 09-15-2023 09-15-2023 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 03-15-2024 07-02-2024 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 04-15-2024 08-02-2024 --- No
Publish Proposed ITA in Federal Register (Agency Action) 11-15-2024 03-04-2025 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 09-01-2025 11-04-2025 --- No
ITA decision rendered (Agency Action) 10-01-2025 12-04-2025 --- No
Planned
The project sponsor’s delayed submission of information needed for a complete Marine Mammal Protection Act (MMPA) Incidental Take Authorization (ITA) application has resulted in delays to the schedule for NMFS’s MMPA. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 09-15-2023 09-15-2023 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 03-15-2024 07-02-2024 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 04-15-2024 08-02-2024 --- No
Publish Proposed ITA in Federal Register (Agency Action) 11-15-2024 03-04-2025 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 09-01-2025 11-04-2025 --- No
ITA decision rendered (Agency Action) 10-01-2025 12-04-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 09-15-2023 09-15-2023 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 03-15-2024 03-15-2024 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 04-15-2024 04-15-2024 --- No
Publish Proposed ITA in Federal Register (Agency Action) 11-15-2024 11-15-2024 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 09-01-2025 09-01-2025 --- No
ITA decision rendered (Agency Action) 10-01-2025 10-01-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 09-15-2023 09-15-2023 --- No
NOAA Determines ITA Application is Complete (Applicant Action) 03-15-2024 03-15-2024 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 04-15-2024 04-15-2024 --- No
Publish Proposed ITA in Federal Register (Agency Action) 11-15-2024 11-15-2024 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 09-01-2025 09-01-2025 --- No
ITA decision rendered (Agency Action) 10-01-2025 10-01-2025 --- No