Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 06-03-2022 06-03-2022 --- Yes
Completed application received (Agency Action) 08-05-2022 08-05-2022 --- Yes
Final decision/agency action (Agency Action) 09-01-2023 05-17-2023 --- Yes
In Progress
Revision of the date for the BLM Milestone for Final decision/agency action is related on the revision of the interrelated USFS Milestone for the Supplemental EIS conclusion. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 06-03-2022 06-03-2022 --- Yes
Completed application received (Agency Action) 08-05-2022 08-05-2022 --- Yes
Final decision/agency action (Agency Action) 09-01-2023 05-17-2023 --- No
In Progress
BLM timeline is being updated to reflect April 30, 2023 for final decision, due to USFS timeline shift.    , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 06-03-2022 06-03-2022 --- Yes
Completed application received (Agency Action) 08-05-2022 08-05-2022 --- Yes
Final decision/agency action (Agency Action) 09-01-2023 04-30-2023 --- No
In Progress
While entering agency information for the initial permitting timetable, an incorrect date was inadvertently entered.  The target date for the Initial Application Received was entered as June 23, 2022 instead of June 3, 2022.  The error was noted and corrected before publishing the complete timetable. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application received (Agency Action) 06-03-2022 06-03-2022 --- Yes
Completed application received (Agency Action) 08-05-2022 08-05-2022 --- Yes
Final decision/agency action (Agency Action) 09-01-2023 09-01-2023 --- No