Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) 11-30-2022 11-17-2022 --- Yes
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action) 01-31-2023 12-23-2022 --- Yes
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) 07-28-2023 04-14-2023 --- Yes
Supplemental EIS process concluded (Agency Action) 08-31-2023 05-15-2023 --- Yes
In Progress
Notice of Availability for Supplemental EIS was published in the Federal Register on April 14, 2023 , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) 11-30-2022 11-17-2022 --- Yes
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action) 01-31-2023 12-23-2022 --- Yes
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) 07-28-2023 04-14-2023 --- Yes
Supplemental EIS process concluded (Agency Action) 08-31-2023 05-15-2023 --- No
In Progress
In response to public requests, the comment period has been extended to 11:59 p.m. EST on February 21, 2023.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) 11-30-2022 11-17-2022 --- Yes
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action) 01-31-2023 12-23-2022 --- Yes
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) 07-28-2023 04-15-2023 --- No
Supplemental EIS process concluded (Agency Action) 08-31-2023 05-15-2023 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) 11-30-2022 11-17-2022 --- Yes
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action) 01-31-2023 12-23-2022 --- Yes
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) 07-28-2023 03-31-2023 --- No
Supplemental EIS process concluded (Agency Action) 08-31-2023 03-31-2023 --- No
In Progress
USDA has reviewed our internal processes and developed an update to the existing timetable accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) 11-30-2022 11-17-2022 --- Yes
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action) 01-31-2023 12-23-2022 --- No
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) 07-28-2023 03-31-2023 --- No
Supplemental EIS process concluded (Agency Action) 08-31-2023 03-31-2023 --- No
In Progress
NOI published on Nov 17, 2022 ahead of schedule , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) 11-30-2022 11-17-2022 --- Yes
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action) 01-31-2023 01-31-2023 --- No
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) 07-28-2023 07-28-2023 --- No
Supplemental EIS process concluded (Agency Action) 08-31-2023 08-31-2023 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent (NOI) or Notice to prepare a Supplemental EIS (Agency Action) 11-30-2022 11-30-2022 --- No
Official Notice of Availability of a Draft Supplemental EIS published in the FR (Agency Action) 01-31-2023 01-31-2023 --- No
Official Notice of Availability of a Final Supplemental EIS published in the FR (Agency Action) 07-28-2023 07-28-2023 --- No
Supplemental EIS process concluded (Agency Action) 08-31-2023 08-31-2023 --- No