Permitting Action Modification History

Complete
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-24-2022 06-24-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-29-2022 07-29-2022 --- Yes
ESA Consultation Concludes (Agency Action) 12-12-2022 12-12-2022 02-28-2023 Yes
Complete
On October 4, 2022, the FWS sent FERC a letter requesting additional information on Mountain Valley Pipeline, LLC’s (MVP) Updated Supplement to the Biological Assessment (SBA2). On October 19, 2022, FERC provided FERC’s and the Service’s comments on the SBA2 to MVP. On November 18, 2022, FERC provided FERC’s and the Service’s consolidated comments on Appendix L of the SBA2 to Mountain Valley, LLC. Since that time, MVP has been providing the requested information to FERC and the FWS.  The FWS needs additional time to review the information from the applicant and in accordance with 50 C.F.R. § 402.14(e) the parties have extended the consultation period by 60 days with the consent of the project sponsor. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-24-2022 06-24-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-29-2022 07-29-2022 --- Yes
ESA Consultation Concludes (Agency Action) 12-12-2022 12-12-2022 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ESA Consultation Request Package Submitted (Agency Action) 06-24-2022 06-24-2022 --- Yes
FWS determines ESA Consultation Package is Complete - Formal (Agency Action) 07-29-2022 07-29-2022 --- Yes
ESA Consultation Concludes (Agency Action) 12-12-2022 12-12-2022 --- No