Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-22-2025 09-16-2025 --- No
Completeness Determination (Agency Action) 05-22-2025 10-16-2025 --- No
Complete application submitted (Applicant Action) 06-06-2025 08-14-2026 --- No
Issuance of Decision (Agency Action) 09-17-2026 02-11-2027 --- No
Planned
With the shift in the ROD date, USACE is accordingly extending the milestone date for issuance of the Section 408 final decision to 120 days post-ROD. Section 408 review is anticipated to conclude on the same date as Section 10/404 action. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-22-2025 09-16-2025 --- No
Completeness Determination (Agency Action) 05-22-2025 10-16-2025 --- No
Complete application submitted (Applicant Action) 06-06-2025 08-14-2026 --- No
Issuance of Decision (Agency Action) 09-17-2026 02-11-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-22-2025 04-22-2025 --- No
Completeness Determination (Agency Action) 05-22-2025 05-22-2025 --- No
Complete application submitted (Applicant Action) 06-06-2025 06-06-2025 --- No
Issuance of Decision (Agency Action) 09-17-2026 09-17-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) --- --- --- No
Completeness Determination (Agency Action) --- --- --- No
Complete application submitted (Applicant Action) --- --- --- No
Issuance of Decision (Agency Action) --- --- --- No