Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 07-05-2024 07-05-2024 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 01-06-2025 05-30-2025 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 02-04-2025 06-30-2025 --- No
Publish Proposed ITA in Federal Register (Agency Action) 09-05-2025 01-30-2026 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 07-20-2026 12-14-2026 --- No
ITA decision rendered (Agency Action) 08-20-2026 01-13-2027 --- No
Planned
The project sponsor notified NMFS that they would not complete the acoustic modeling for their MMPA incidental take authorization application until the end of February, which caused the milestone for determining the application complete to be extended.  This extension required revisions to the subsequent MMPA milestones as well as revisions to the ESA/EFH milestones, per the dependencies and inter-relatedness of the milestones.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 07-05-2024 07-05-2024 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 01-06-2025 05-30-2025 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 02-04-2025 06-30-2025 --- No
Publish Proposed ITA in Federal Register (Agency Action) 09-05-2025 01-30-2026 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 07-20-2026 12-14-2026 --- No
ITA decision rendered (Agency Action) 08-20-2026 01-13-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 07-05-2024 07-05-2024 --- Yes
NOAA Determines ITA Application is Complete (Applicant Action) 01-06-2025 01-06-2025 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 02-04-2025 02-04-2025 --- No
Publish Proposed ITA in Federal Register (Agency Action) 09-05-2025 09-05-2025 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 07-20-2026 07-20-2026 --- No
ITA decision rendered (Agency Action) 08-20-2026 08-20-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 07-05-2024 07-05-2024 --- No
NOAA Determines ITA Application is Complete (Applicant Action) 01-06-2025 01-06-2025 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 02-04-2025 02-04-2025 --- No
Publish Proposed ITA in Federal Register (Agency Action) 09-05-2025 09-05-2025 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 07-20-2026 07-20-2026 --- No
ITA decision rendered (Agency Action) 08-20-2026 08-20-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) --- --- --- No
NOAA Determines ITA Application is Complete (Applicant Action) --- --- --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) --- --- --- No
Publish Proposed ITA in Federal Register (Agency Action) --- --- --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) --- --- --- No
ITA decision rendered (Agency Action) --- --- --- No