Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 01-22-2025 03-07-2025 06-05-2025 No
NOAA determines EFH Assessment is Complete (Agency Action) 09-05-2025 01-30-2026 04-30-2026 No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 12-04-2025 04-30-2026 07-29-2026 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 01-22-2025 03-07-2025 06-05-2025 No
NOAA determines EFH Assessment is Complete (Agency Action) 09-05-2025 01-30-2026 04-30-2026 No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 12-04-2025 04-30-2026 07-29-2026 No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 01-22-2025 03-07-2025 06-05-2025 No
NOAA determines EFH Assessment is Complete (Agency Action) 09-05-2025 01-30-2026 04-30-2026 No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 12-04-2025 04-30-2026 07-27-2026 No
Planned
The interim milestone, “EFH Consultation Request Submitted” is aligned with the date BOEM submits the draft DEIS for cooperating agency review and is contingent on NMFS receiving a consultation request from BOEM (as lead Federal agency), consisting of a draft EFH assessment, that considers the effects of all proposed Federal actions. The interim milestone, “NOAA Determines EFH Assessment Complete,” is contingent upon NMFS receiving sufficient information to deem the package complete and initiate EFH consultation. This includes receipt of a complete EFH assessment responding to any previous information requests, a copy of reports referenced in the EFH assessment, and public availability of the DEIS from the lead agency. This milestone is set to align with ESA. The final milestone, “NOAA Issues any EFH CRs,” should be 90 days after NMFS determines the EFH assessment is complete. Note that the Milestone date for publication of the Final EIS date must allow adequate time for incorporation of the findings of the ESA consultation into the Final EIS. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 01-22-2025 03-07-2025 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 09-05-2025 01-30-2026 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 12-04-2025 04-30-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) 01-22-2025 01-22-2025 --- No
NOAA determines EFH Assessment is Complete (Agency Action) 09-05-2025 09-05-2025 --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) 12-04-2025 12-04-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
EFH Consultation Request Submitted – EFH Assessment (Agency Action) --- --- --- No
NOAA determines EFH Assessment is Complete (Agency Action) --- --- --- No
NOAA Issues any EFH Conservation Recommendations (Agency Action) --- --- --- No