Permitting Action Modification History

Planned
The result of delay of ASOW N submittal of the MMPA ITA application is shifting the remaining NEPA milestone dates. The Section 10/404 Final decision milestone is dependent on the NEPA timeline. The Section 10/404 final completion date is dependent upon the final completion date of BOEM’s NEPA action. For this project, the USACE review will require 120 days between issuance of the ROD and issuance of USACE’s Section 10/404 decision. Therefore, an extension of the Section 10/404 final completion date is requested based upon the extension of the ROD milestoneThe Section 10/404 final completion date is dependent upon the final completion date of BOEM’s NEPA action. For this project, the USACE review will require 120 days between issuance of the ROD and issuance of USACE’s Section 10/404 decision. Therefore, an extension of the Section 10/404 final completion date is requested based upon the extension of the ROD milestone
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-22-2025 09-16-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-22-2025 10-16-2025 --- No
Publication of Public Notice (Agency Action) 06-06-2025 10-31-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-17-2026 02-11-2027 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 04-22-2025 04-22-2025 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 05-22-2025 05-22-2025 --- No
Publication of Public Notice (Agency Action) 06-06-2025 06-06-2025 --- No
Final Verification/Permit Decision Rendered (Agency Action) 09-17-2026 09-17-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) --- --- --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) --- --- --- No
Publication of Public Notice (Agency Action) --- --- --- No
Final Verification/Permit Decision Rendered (Agency Action) --- --- --- No