Permitting Action Modification History

Paused
project pause , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 02-18-2022 02-18-2022 --- Yes
Application deemed complete (Agency Action) 03-21-2022 03-21-2022 --- Yes
Final decision/agency action (Agency Action) 09-29-2025 --- --- No
Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 02-18-2022 02-18-2022 --- Yes
Application deemed complete (Agency Action) 03-21-2022 03-21-2022 --- Yes
Final decision/agency action (Agency Action) 09-29-2025 12-28-2025 --- No
In Progress
The Construction and Operation Plan (COP) milestone is dependent on the NEPA schedule and will shift accordingly. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 02-18-2022 02-18-2022 --- Yes
Application deemed complete (Agency Action) 03-21-2022 03-21-2022 --- Yes
Final decision/agency action (Agency Action) 09-29-2025 12-28-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 02-18-2022 02-18-2022 --- Yes
Application deemed complete (Agency Action) 03-21-2022 03-21-2022 --- Yes
Final decision/agency action (Agency Action) 09-29-2025 09-29-2025 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) --- 02-18-2022 --- Yes
Application deemed complete (Agency Action) --- 03-21-2022 --- Yes
Final decision/agency action (Agency Action) --- --- --- No