Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 11-29-2022 01-15-2027 --- No
Completeness Determination (Agency Action) 01-30-2023 02-16-2027 --- No
Complete application submitted (Applicant Action) 12-29-2024 04-16-2027 --- No
Issuance of Decision (Agency Action) 02-27-2026 04-14-2028 --- No
Planned
The applicant had initially requested a review schedule for their Kitty Hawk South project with an early NOI coming in October 2022 with the DEIS NOA occurring much later in 2024 - this timeframe has been extended.  USACE milestones were adjusted accordingly.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 11-29-2022 01-15-2027 --- No
Completeness Determination (Agency Action) 01-30-2023 02-16-2027 --- No
Complete application submitted (Applicant Action) 12-29-2024 04-16-2027 --- No
Issuance of Decision (Agency Action) 02-27-2026 04-14-2028 --- No
Planned
The applicant had initially requested a review schedule for their Kitty Hawk South project with an early NOI coming in October 2022 with the DEIS NOA occurring much later in 2024 - this timeframe has been extended, with an NOA date in Feb 2026 and a ROD date in Jan 2027.  USACE milestones were adjusted accordingly.  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 11-29-2022 01-21-2026 --- No
Completeness Determination (Agency Action) 01-30-2023 02-20-2026 --- No
Complete application submitted (Applicant Action) 12-29-2024 04-22-2026 --- No
Issuance of Decision (Agency Action) 02-27-2026 02-27-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) --- 11-29-2024 --- No
Complete application submitted (Applicant Action) --- 12-29-2024 --- No
Completeness Determination (Agency Action) --- 01-30-2023 --- No
Issuance of Decision (Agency Action) --- 02-27-2026 --- No