Permitting Action Modification History

Planned
The applicant had initially requested an extended review schedule for their Kitty Hawk South project with an early NOI coming in October 2022 with the DEIS NOA occurring much later in 2024.  The applicant has now requested that the NOI instead come later.  In order to conform to the NOI checklist, the NOI would come on approximately January 12, 2024.  USACE milestones were adjusted accordingly.  Since the previous update, the schedule has shifted again and the USACE timetable was adjusted accordingly.
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) 11-29-2024 01-15-2027 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) 12-14-2024 02-02-2027 --- No
Publication of Public Notice (Agency Action) 12-29-2024 02-16-2027 --- No
Final Verification/Permit Decision Rendered (Agency Action) 02-27-2026 04-14-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Pre-construction Notification (PCN)/Form ENG 4345/Joint Application Form Received (Applicant Action) --- 11-29-2024 --- No
Complete Pre-Construction Notification (PCN)/Application Received (Applicant Action) --- 12-14-2024 --- No
Publication of Public Notice (Agency Action) --- 12-29-2024 --- No
Final Verification/Permit Decision Rendered (Agency Action) --- 02-27-2026 --- No