Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 02-29-2024 04-16-2026 --- No
NOAA Determines ITA Application is Complete (Applicant Action) 08-29-2024 10-15-2026 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 09-30-2024 11-16-2026 --- No
Publish Proposed ITA in Federal Register (Agency Action) 02-27-2025 04-15-2027 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 12-30-2025 02-15-2028 --- No
ITA decision rendered (Agency Action) 01-29-2026 03-16-2028 --- No
Planned
Updated milestones based on BOEM's revised EIS schedule, which extended 777 days from original dates at the project sponsor's request. All milestones have been adjusted accordingly  , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) 02-29-2024 04-16-2026 --- No
NOAA Determines ITA Application is Complete (Applicant Action) 08-29-2024 10-15-2026 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) 09-30-2024 11-16-2026 --- No
Publish Proposed ITA in Federal Register (Agency Action) 02-27-2025 04-15-2027 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) 12-30-2025 02-15-2028 --- No
ITA decision rendered (Agency Action) 01-29-2026 03-16-2028 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
ITA Application Submitted (Applicant Action) --- 02-29-2024 --- No
NOAA Determines ITA Application is Complete (Applicant Action) --- 08-29-2024 --- No
Publish Notice of Receipt in Federal Register (LOA Only) (Agency Action) --- 09-30-2024 --- No
Publish Proposed ITA in Federal Register (Agency Action) --- 02-27-2025 --- No
Publish Final ITA Regulations in Federal Register (LOA Only) (Agency Action) --- 12-30-2025 --- No
ITA decision rendered (Agency Action) --- 01-29-2026 --- No