Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-14-2022 04-14-2022 --- Yes
Application deemed complete (Agency Action) 05-03-2022 05-03-2022 --- Yes
Final decision/agency action (Agency Action) 01-28-2026 04-14-2028 --- No
In Progress
The new schedule accommodates the timing of offshore surveys and the submission of additional information needed for the NEPA process and environmental permitting.  The Project Sponsor requested that BOEM extend the Project permitting timetable by two years to allow the Project Sponsor additional time to explore options for paths to market. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) 04-14-2022 04-14-2022 --- Yes
Application deemed complete (Agency Action) 05-03-2022 05-03-2022 --- Yes
Final decision/agency action (Agency Action) 01-28-2026 04-14-2028 --- No
In Progress
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) --- 04-14-2022 --- Yes
Final decision/agency action (Agency Action) --- 01-28-2026 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Initial application submitted (Applicant Action) --- 04-14-2022 --- No
Final decision/agency action (Agency Action) --- 01-28-2026 --- No