Permitting Action Modification History

Paused
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 10-21-2022 12-15-2025 --- No
Scoping (Agency Action) 11-07-2022 02-18-2026 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 12-29-2024 02-15-2027 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 09-12-2025 10-29-2027 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 10-31-2025 12-16-2027 --- No
Planned
The new schedule accommodates the timing of offshore surveys and the submission of additional information needed for the NEPA process and environmental permitting. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 10-21-2022 12-15-2025 --- No
Scoping (Agency Action) 11-07-2022 02-18-2026 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 12-29-2024 02-15-2027 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 09-12-2025 10-29-2027 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 10-31-2025 12-16-2027 --- No
Planned
Applicant has requested a schedule change. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 10-21-2022 01-12-2024 --- No
Scoping (Agency Action) 11-07-2022 01-29-2024 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 12-29-2024 12-29-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 09-12-2025 09-12-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 10-31-2025 10-31-2025 --- No
Planned
The NOI is moving out to allow for more timely consultation with interested parties regarding supplemental submissions of plan details already scheduled for late 2023. , basic_html
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) 10-21-2022 01-12-2024 --- No
Scoping (Agency Action) 11-07-2022 11-07-2022 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) 12-29-2024 12-29-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) 09-12-2025 09-12-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) 10-31-2025 10-31-2025 --- No
Planned
N/A
Milestone Original Target Date Current Target Date Alternative Completion Date Milestone Complete?
Issuance of Notice of Intent to prepare an Environmental Impact Statement (EIS) (Agency Action) --- 10-21-2022 --- No
Scoping (Agency Action) --- 11-07-2022 --- No
Official Notice of Availability of a Draft EIS published in the Federal Register (FR) beginning both the public comment period and concurrent CAA Section 309 Review (Agency Action) --- 12-29-2024 --- No
Official Notice of Availability of a Final EIS published in the FR beginning both the public review period and concurrent CAA Section 309 Review (Agency Action) --- 09-12-2025 --- No
Issuance of Lead Agency Record of Decision (Agency Action) --- 10-31-2025 --- No