USA Banner

Official US Government Icon

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

Secure Site Icon

Secure .gov websites use HTTPS
A lock ( ) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

FAST-41 Covered Projects Postings by Agencies for White Pine Pumped Storage

FAST-41 Initiation Notice
Application and Supporting Documents

The project sponsor filed an application for an original license on February 27, 2023.  The application and other supporting documents can be found by searching under docket number P-14851 in the Commission’s eLibrary system.

Information on the status of mitigation measures

Commission staff will include any staff-recommended mitigation measures in this section after issuance of the draft and final National Environmental Policy Act documents. 

Description of the status of any litigation

There is no active litigation on the Commission’s licensing proceeding.

Information about project-related public meetings, public hearings, and public comment periods

Information on the timing of project-related comment periods and public meetings will be added to this section as it becomes available.  

  • On September 23, 2024, the Commission issued a notice establishing a deadline for filing scoping comments and providing information on public scoping meetings and an environmental site review.
Description of any Federal agency action taken or decision made that materially affects the status of the project