FAST-41 Covered Projects Postings by Agencies for Seminoe Pumped Storage Project

FAST-41 Initiation Notice

Lead agency will provide FIN

Application and Supporting Documents

USACE received a request for a Department of the Army Permit on September 28, 2023.

Information on the status of mitigation measures

The Corps requires that applicants consider and use all reasonable and practical measures to avoid and minimize impacts to aquatic resources. If the applicant is unable to avoid or minimize all impacts, the Corps may require compensatory mitigation. The applicant has proposed to pursue mitigation approaches which may consist of either mitigation banking or “in lieu fee,” in which any such mitigation approaches would be developed in coordination with federal agencies.  In any case, unavoidable impacts to aquatic resources, and resulting adverse effects to the aquatic environment, would be offset via compensatory mitigation and would comply with the 2008 Mitigation Rule. 

Description of the status of any litigation

N/A

Information about project-related public meetings, public hearings, and public comment periods

FERC hosted public scoping meetings in 2024.  USACE has not hosted a pubic hearing or meeting in association with the DA permit review. 

Description of any Federal agency action taken or decision made that materially affects the status of the project

A 30-day public notice was published on October 16, 2023.  The notice is available here: extension://efaidnbmnnnibpcajpcglclefindmkaj/https://usace.contentdm.oclc.org/utils/getfile/collection/p16021coll15/…;