FAST-41 Covered Projects Postings by Agencies for Seminoe Pumped Storage Project

Application and Supporting Documents

The project sponsor filed an application for an original license on January 18, 2023.  The application and other supporting documents can be found by searching under docket number P-14787 in the Commission’s eLibrary system.

Information on the status of mitigation measures

On June 12, 2026, the Commission issued a final Environmental Impact Statement discussing proposed and recommended environmental measures for the proposed project. 

Description of the status of any litigation

There is no active litigation on the Commission’s licensing proceeding.

Information about project-related public meetings, public hearings, and public comment periods

Information on the timing of project-related comment periods and public meetings will be added to this section as it becomes available. 

  • On September 6, 2024, the Commission issued a notice establishing a deadline for filing scoping comments, and providing information on public scoping meetings and an environmental site review.
  • On January 13, 2025, the Commission issued a notice establishing a deadline for filing comments, recommendations, terms and conditions, and prescriptions. 
  • On March 28, 2025, the Commission issued a notice establishing a deadline for filing additional comments on the scope of issues to address in the Environmental Impact Statement.
  • On September 26, 2025, the Commission issued a notice with information on submitting written comments and attending public comment sessions on the draft Environmental Impact Statement.  
  • On January 23, 2026, the Commission issued a notice extending the comment period on the draft Environmental Impact Statement.
  • On September 11, 2026, the Commission issued a notice establishing a deadline for filing comments on the scope of issues to address in the supplemental Environmental Impact Statement.  
Description of any Federal agency action taken or decision made that materially affects the status of the project