FAST-41 Covered Projects Postings by Agencies for Robert C. Byrd Hydroelectric Project

Application and Supporting Documents

The project sponsor filed an application for an original license on January 23, 2025. The application and other supporting documents can be found by searching under docket number P-15094 in the Commission's eLibrary system.

Information on the status of mitigation measures

On September 28, 2026, Commission staff issued an Environmental Assessment discussing proposed and recommended environmental measures for the proposed project. 

Description of the status of any litigation

There is no active litigation on the Commission's licensing proceeding.

Information about project-related public meetings, public hearings, and public comment periods

Information on the timing of project-related comment periods and public meetings will be added to this section as it becomes available.

  • On September 25, 2025, the Commission issued a notice establishing a deadline for filing scoping comments.
  • On January 14, 2026, the Commission issued a notice establishing a deadline for filing comments, recommendations, terms and conditions, and prescriptions. 
  • On September 28, 2026, the Commission issued a notice with information on submitting comments on the Environmental Assessment. 
Description of any Federal agency action taken or decision made that materially affects the status of the project